Donges pushes bridge Overfly over Nuremberg East interchange

The bridge structure 3-1 Overfly transfers an exit of the motorway A6 Rifa Amberg over the motorway junction Nuremberg East and thus reconnects the motorway A6 to the motorway A9. The new construction will improve the performance of the Nuremberg East junction.

The bridge construction is a combination of continuous girder and cable-stayed bridge and can therefore be classified as an extradosed bridge. Donges SteelTec is constructing the complete bridge in the so-called cycle basement in 6 sections. After assembly, each section is hydraulically shifted longitudinally over the abutment and the concrete piers. The next section is then connected to the displaced end of the previous section until the opposite abutment is reached.

The steel composite structure, 588 m long in total, impressively spans the 115 m span with a total of 5 pairs of pylons. Up to 55 stranded cables form the cables of the stay cables. A total of approx. 8,600 tons of steel will be used for the 588 m long bridge.

The displacement of the bridge, including the already assembled pylons and cables, is carried out in 6 cycles with the maximum displacement distances of 115 m. A 50 m long cantilever bridges the free spans during shifting and compensates for the deflections of the bridge due to its own weight when it runs onto the next pier. Shifting takes two days per cycle. It takes place on special shifting rockers and is carried out with the help of greased shifting plates that allow the steel construction to slide forward successively. In this way, the shifting load that the hydraulic presses have to apply can be reduced to a maximum of 10 % of the bridge weight.

On 22.06.2023 the 3rd shifting cycle was successfully completed, the next components of the 4th cycle are currently being assembled. The steel construction work will continue until 2024.

 

Donges SteelTec builds bar arch bridge for the Regionaltangente West (RTW) in Frankfurt am Main

An impressive bar arch bridge is currently being built at the Frankfurt Stadion S-Bahn station and thus right in front of the Waldstadion Frankfurt. The bridge structure carries the new RTW line over the existing Deutsche Bahn AG track system.

The superstructure of the bar arch bridge with a span of approx. 113 m is being built in steel construction and is divided into two arch levels consisting of stiffening girders, arches and hangers, as well as an orthotropic carriageway and walkways with cable ducts on both sides.

Design, fabrication and corrosion protection of the steel components were carried out at the Donges SteelTec GmbH plant in Darmstadt.

Parallel to the fabrication, the individual foundations were produced on the construction site and the auxiliary scaffolding was prepared for the erection. The steel structures were delivered by heavy-duty transporters to the pre-assembly site, where a mobile crane placed the components directly into the assembly position. Due to the very tight space conditions on the construction site, the pre-assembly began in the eastern area of the assembly area. Here, the first third of the superstructure with axis 10 was assembled in a horizontal position and then moved along the assembly area in a westerly direction using an SPMT (Self-Propelled Modular Transporter) so that the other steel sections could then be added.  Welding and corrosion protection work is currently underway on the site until autumn 2023.

For the actual insertion over the DB tracks in May 2024, the superstructure will be stacked in the storage axles to shunting height, transferred to SPMT and aligned in the shunting position. During a 24-hour break in rail traffic, the superstructure will be pushed over the track field with maximum cantilever and taken over on the opposite side by a lattice boom crawler crane.

We are very pleased to be able to carry out this exciting project close to home.

 

One of the highest railway bridges in Europe gets a new steel superstructure

At 96 m, the Jauntal Bridge in Austria is one of the highest railway bridges in Europe. In the course of the construction of the new double-track Koralmbahn railway line, the existing single-track structure of the Jauntal Bridge will be upgraded to a modern, double-track steel truss composite structure. Donges SteelTec has been awarded the contract for the manufacture, delivery and assembly of the steel superstructure. The 3300 tonne steel structure will be manufactured at the Darmstadt plant. The 428 m long steel structure will first be assembled in three segments on a pre-assembly area below the existing bridge. The three structural elements are then moved transversely and longitudinally one after the other. In the process, the old and new supporting structures are connected to each other and the existing bridge is also pushed out.

The spectacular assembly work high above the river Drava begins in early January, when the first of the three segments of the new superstructure is first shifted transversely and then coupled to the existing structure. The first longitudinal shift will then follow in February. A technical and logistical challenge for our employees and, after the Danube bridge in Linz (bypass bridges), another milestone for our company in neighbouring Austria.

 

Bridge construction division is pleased with major contract for the replacement construction of the Pfaffendorfer Bridge in Koblenz

Donges SteelTec, as part of the ARGE Pfaffendorfer Brücke consortium, has been awarded the contract for the replacement construction of the Pfaffendorfer Bridge in Koblenz.

As an important link across the Rhine, the existing bridge must be completely replaced by a new one. For this purpose, the 311 m long steel composite bridge, which is broken up in the area of the pier coves, will first be built in the lateral position next to the existing bridge and, after the demolition of the existing bridge, will be moved transversely into the final position.

Donges SteelTec is taking over the technical responsibility for the entire structure by preparing the structural analysis of the river bridge, the assembly planning and the execution and workshop drawings within the consortium. Around 5,500 tonnes of steel structure will be manufactured and corrosion-protected in the halls of Donges SteelTec GmbH in Darmstadt. Afterwards, the steel elements, weighing up to 450 tonnes, will be successively transported by ship via a pre-assembly site on the Rhine to the construction site, where they will be assembled above the Rhine by means of floating cranes.

The work for the new Rhine bridge will be carried out between 2023 and 2027

 

 

Donges SteelTec moves 1400-ton steel bridge of the motorway A73 into final position

Even storm “Zeynep” and “Antonia” could not stop our technicians: At the end of February, the second superstructure of the motorway bridge in the direction of Bamberg was shifted at the A73 junction Breitengüßbach Süd. The steel structure, which weighs around 1,400 tonnes, is 150 metres long and approx. 18 metres wide, was pushed into its final position over the weekend across the B 4 trunk road, the railway tracks and a field path. Completion of the 3-span steel composite bridge is planned for autumn 2022.

First steel component of the 7-span Thulba viaduct shifted.

Darmstadt/Oberthulba, June 2021. Last weekend, the first longitudinal shifting of the steel superstructure for the new Thulba viaduct took place. The steel colossus was moved 66 m. However, the high summer temperatures on Friday not only caused problems for our assembly team, but also for the steel structure. This resulted in deformations of the steel component due to uneven heating. However, our experienced fitters quickly found a solution to this unforeseen challenge, so that the final position of the bridge section was reached on schedule on Saturday morning.

The replacement of the Thulba viaduct is a steel composite bridge with two superstructures, which crosses the A7 between Würzburg and Fulda in the Bad Kissingen/Oberthulba section. The bridge has a total length of 460 m each and runs up to 53 m above the valley. The steel structure tonnage totals 6,000 tonnes.

 

With the red bridge over the Rheinstraße Donges SteelTec sets an imprressive new accent on urban development in Darmstadt

The new bridge over Darmstadt’s most important access road provides an important new pedestrian and cycle link between the Europaviertel with the main railway station and the new Rhein-Main telecommunications centre.

The aim was to preserve the tree population as far as possible. For this reason, the bridge swings over the Rheinstraße and playfully winds its way between the trees with its long ramps.

The bridge consists of a steel construction made in our factory in Darmstadt, it is 318 metres long and three metres wide. 370 tonnes of steel go into the structure, which rests on V-shaped supports.

While it is finished in steel grey on the outside, the stairs, access road and zebra crossing are designed in bright red. LED lighting is fully integrated into the handrails. In the evening and night hours, it illuminates the entire course of the bridge and the red interior colour begins to shine.

After the construction of the Dornheimer Weg Bridge in 1910 and its renovation in 2002, we are proud to have once again set an urban accent in Darmstadt with the new bridge over the Rheinstraße.

Two new Steigerwald motorway bridges in just one night

During the last operation, it was only one bridge, this time we increased the operation and installed two steel hollow box girders for the country road bridges over the A3 near Erlangen in only one night.

For this, the section between Heßdorf and Höchstadt an der Aisch was completely closed for 14 hours.

In order to keep the closure of the motorway as short as possible, two different pre-assembly sites with wide access to the motorway had been set up beforehand. Here, the 4 bridge parts prefabricated in our factory in Darmstadt were welded together to form the two 260 and 380 tonne and 70 meter long steel colossi.

In order to transport the two bridges in their full size to the actual construction site, a complicated and unusual technique was required. Two self-propelled heavy-duty transport modules (SPMT) were used for this purpose. They brought the bridge constructions at walking pace over the closed motorway to the places where they were set down free-floating, centimetre by centimetre, at their destination.

The 70 km long motorway section in the Steigerwald between Würzburg and Erlangen will be renewed by 2025. Another 19 steel composite bridges will be installed in the same way.

Successfully connected! “Bridge closure” for the 1st construction phase of the Grumbachtal Bridge.

Darmstadt/St. Ingbert

In mid-February, the last two components, the so-called “bridge closure”, for the 1st construction phase of the Grumbachtal Bridge were successfully assembled.

Even before that, there had been a lot to marvel at in St. Ingbert when the first six bridge components were lifted into place. With the help of a caterpillar crane specially set up for the lifting operation, our assembly team managed to lift the huge steel structures into their final position in a very confined space.

Now the lifting oft he last two mighty bridge sections, each with a length of around 22 metres and a weight of up to 60 tonnes, was once again spectacular. For the crane’s crossing, which was only allowed to take place at night, the traffic over the bridge had to be slowed down for a short time and for the actual lifting, the motorway in the direction of Saarbrücken was even completely closed for several hours, as the components were unloaded on the motorway, turned and then lifted into their final position.

On Sunday, 15 February, the time had come and the first construction phase could be completed precisely and on schedule. The fact that this went so smoothly is largely due to the precise planning work of the responsible assembly engineer and our well-rehearsed, experienced assembly team on site. The components are now being welded together.

At the end of March, our assembly team will leave the construction site as planned and will not return until the second construction phase can probably be assembled in 2022.

Installation of the first Steigerwald freeway bridge in just one night

Darmstadt, 29.11.2020. Our assembly engineers only had one night to install the 260-ton highway bridge over the A3. For this purpose, the A3 was completely closed off between Schlüsselfeld and Höchstadt-Nord.

The preparations had already begun weeks earlier with the installation of a pre-assembly area on a former freeway parking lot shortly before the Schlüsselfeld exit. There the four steel bridge sections manufactured at our plant in Darmstadt were first welded together to form a 70 meter long and 260 ton bridge structure.

Two self-propelled modular transporters (SPMT) transported the bridge structure at walking speed over the closed highway to the construction site two kilometers away, where it was then placed in the bridge bearings, centimeter by centimeter, free-floating.

By 2024, a further 21 steel composite bridges will be installed over the Steigerwald motorway.