A3 Steigerwald Motorway

Installation of the first Steigerwald freeway bridge in just one night

Darmstadt, 29.11.2020. Our assembly engineers only had one night to install the 260-ton highway bridge over the A3. For this purpose, the A3 was completely closed off between Schlüsselfeld and Höchstadt-Nord.

The preparations had already begun weeks earlier with the installation of a pre-assembly area on a former freeway parking lot shortly before the Schlüsselfeld exit. There the four steel bridge sections manufactured at our plant in Darmstadt were first welded together to form a 70 meter long and 260 ton bridge structure.

Two self-propelled modular transporters (SPMT) transported the bridge structure at walking speed over the closed highway to the construction site two kilometers away, where it was then placed in the bridge bearings, centimeter by centimeter, free-floating.

By 2024, a further 21 steel composite bridges will be installed over the Steigerwald motorway.