A6 Grumbachtalbrücke
Assembly start of the 2nd construction phase of the Grumbach Valley Bridge near St. Ingbert
In April 2023, construction work on the 1st construction phase of the Grumbach Valley Bridge was completed and traffic was diverted to the newly constructed structure. Following the demolition of the existing structure and the construction of the first substructures, our assembly team has now set up the construction site for the assembly of the steel structure of the 2nd construction phase (substructure 1) for the Mannheim direction of travel.
In the first assembly phase, two auxiliary supports were erected over the past few weeks to store the 262-tonne steel structures. The first large components were then transported overnight from our plant in Darmstadt to the construction site in Saarland using heavy goods vehicles. There they were first turned on the ground and then lifted into their final position using two 650 tonne mobile cranes. Once the steel parts had been successfully lifted into place, the component joints were welded and then coated with corrosion protection.
A total of 22 sections and 6 cross beams for the entire substructure are assembled in this way.