A7 Voest Viaduct in Linz

The first bridge section was achieved

Darmstadt/Linz 24.06.2019.
On Friday, 21.06.2019 the middle section of the bypass bridges in Linz was successfully erected. The 950 t heavy and over 90 m long bridge section was moved into position by ship and pulled into end position by steel cables. Thus, the first bridge section of approx. 3500 t across the Danube was achieved. Next week a further bridge section will be erected in Urfahr in the bank area and the preparatory work for the second bypass bridge has also begun with the first deliveries to the pre-assembly site.