EÜ Erbach – New project for our bridge construction team

A new tied-arch bridge will be built near Bad Camberg in 2025

Congratulations to our bridge construction team on the new contract! Together with the construction company Albert Weil AG, we have been commissioned by DB Netz AG to build the new Erbach railway overpass near Bad Camberg.

Approx. 720 tonnes of steel are required for the 2-track tied arch superstructure with reinforced concrete abutments. The entire steel structure will be manufactured at our plant in Darmstadt and then transported to the construction site in central Hesse using heavy goods vehicles. There, the components will be welded together at the pre-assembly site to form the approx. 60 metre long bar arch and then the supporting structure will be driven into its final position in October 2025 using SPMTs (Self-Propelled Modular Transporters). A particular challenge for our assembly crew will be to install the bridge precisely during a shutdown period.