Movement of launchpad successfully completed

By the end of August, the pad was welded on a pre-assembly surface. After these tasks were completed, the pad was successfully moved to its final position on September 11, 2018 and subsequently de-stacked onto the concrete slab. The final construction phase is currently underway.

The installation of the supply mast will follow in mid-October.