MERCK Stadium at Böllenfalltor

New back straight inaugurated at the Merck Stadium

Darmstadt, 02.02.2020. The assembly work of the steel roof construction for the new back straight in the Darmstadt stadium was completed on schedule. The first match of the Lilies could thus take place on February 2 as planned in front of the new backdrop.

Around 400 tons of steel were required for the construction of the new grandstand roof. In addition to the roof structure, Donges SteelTec also supplied and installed the roof and wall cladding.