Successful pylon installation on the Steigerwald motorway

Another milestone was reached on the A3 Steigerwald motorway last Wednesday: the pylons of the BW314a structure were successfully moved into position by the Donges installation team. This bridge is the twenty-first of a total of 22 planned steel structures and the first cable-stayed bridge in the project.

The pylons are technically challenging as they are inclined in two directions when viewed from above. The cross-section tapers towards the top. The pylons were assembled using two mobile cranes. Thanks to a hinged construction, the mobile cranes were then able to erect the pylons safely and precisely. There was a critical tilting moment during which the pylon swung through on the crane hook. This method made it possible to bring the pylon into a vertical position in a controlled manner and at the same time anchor it to the intended attachment points.

The bridge was planned almost exclusively with the help of 3-dimensional models, which made the construction and assembly planning much more precise.

In terms of steel construction, the BW314a structure is probably the most beautiful and challenging bridge on the Steigerwald motorway. As a cable-stayed bridge, it will attract attention above all through its architectural aesthetics.

With the successful erection of the pylons, the major project is nearing completion, at least as far as the steel construction is concerned.

The A3 Steigerwald motorway is a major infrastructure project that is of great importance for both local and national traffic.The expansion and modernisation of the route is expected to significantly improve road safety and traffic flow.

The client and the companies involved can look back with pride on the work carried out so far, which has paved the way for a modern and efficient transport artery through the Steigerwald.

Penultimate shifting cycle of the Overfly bridge over the Nuremberg East motorway junction successfully completed

The penultimate shifting cycle of the Overfly bridge structure was successfully completed by the Donges SteelTec assembly team.

The so-called extradosed bridge was moved into its final position using the incremental launching method. The steel superstructure of the bridge is prefabricated in sections at one end of the bridge on the pre-assembly site. From there, it is then moved to the opposite end of the bridge.

The incremental launching method makes it possible to avoid interfering with traffic as far as possible, as the bridge is moved across the motorway junction above the clearance of the lanes.

The Overfly bridge, including the already installed pylons and cables, is shifted in 6 cycles with a maximum shifting distance of 115 metres. The 50-metre-long stem spade bridges the free spans during the shifting process and compensates for the deflection of the bridge due to its own weight when it hits the next pier. Shifting takes two days per cycle. It takes place on special shifting rockers and is carried out with the aid of special shifting plates that allow the steel structure to slide forwards successively. This allows the shunting load that the hydraulic presses have to apply to be reduced accordingly.

The composite steel construction, which is 588 metres long in total, spans the individual support spans of 115 metres impressively with a total of 5 pairs of pylons. Up to 55 stranded cables form the cables of the stay cables. A total of approx. 8,600 tonnes of steel will be used for the 588 m long bridge.

The components of the 6th cycle will be assembled over the next few months. The final shifting will take place in autumn 2024.

Bar arch bridge for the western regional bypass in Frankfurt lifted into place with great precision.

Darmstadt, 03.06.2024. In a spectacular operation, the 1300-tonne tied-arch bridge with a span of 113 metres was installed in its final position over the railway tracks of the Frankfurt-Mannheim line at the Waldstadion in Frankfurt am Main on Friday. This makes the future route of the Regional Tangent West (RTW) clearly visible for the first time: its light rail vehicles are scheduled to run over the bridge from 2028.

The Donges SteelTec assembly team began preparations for the final assembly of the bridge on Wednesday. In order to hoist the steel colossus into position, it was first stored on two huge mobile platforms (SPMT) in the days leading up to its installation. The self-propelled modular transporters with their 288 individually steerable wheels were set in motion late on Corpus Christi evening and manoeuvred the bridge as close as possible to the tracks. A lattice boom crawler crane then took over on the opposite side of the tracks and gently lifted the steel giant over the tracks.

A total of 500 tonnes of counterweights were needed so that the crane monster could hold half the bridge load of 680 tonnes. These were brought in by 20 articulated lorries, while 70 lorry transports were needed to erect the crane. For hours on Friday morning, the bridge was suspended from the crane on one side while it was attached to the eastern abutment. At midday, the crane then lowered the striking tied-arch bridge onto the western abutment, accompanied by applause from the numerous spectators. The work seemed slow, but the time pressure was great. Deutsche Bahn had only closed the railway line between Niederrad and the airport for 24 hours.

The Donges team on site was visibly satisfied and proud of the smooth installation process. ‘On a lift like this, it’s important that everyone knows what their job is and that everyone communicates well with each other. We are an experienced and well-rehearsed team and recognise our responsibility for the safety of those involved and the structure. A big thank you to everyone who made this great engineering achievement possible,’ says the responsible Donges project manager, Aaron von der Heyden.

On Thursday, 2 May 2024, the official start of construction of the Mainflingen Main Bridge took place. Over the next 7 years, the replacement construction of the 450 metre long bridge will be realised by the consortium Adam Hörnig Baugesellschaft mbH & Co. KG and Donges SteelTec GmbH. The current bridge is a three-span tension chord construction with a span of 62.5 – 135 – 62.5 metres. It is followed by a 190 metre long foreshore bridge in prestressed concrete construction.

The federal government is investing around 192 million euros in this construction project. It is due to be opened to traffic in 2031

A 3D model of the Mainflingen Main Bridge, which was created on the basis of BIM planning, gave the guests on this day an impression of this challenging bridge construction project.

A new tied-arch bridge will be built near Bad Camberg in 2025

Congratulations to our bridge construction team on the new contract! Together with the construction company Albert Weil AG, we have been commissioned by DB Netz AG to build the new Erbach railway overpass near Bad Camberg.

Approx. 720 tonnes of steel are required for the 2-track tied arch superstructure with reinforced concrete abutments. The entire steel structure will be manufactured at our plant in Darmstadt and then transported to the construction site in central Hesse using heavy goods vehicles. There, the components will be welded together at the pre-assembly site to form the approx. 60 metre long bar arch and then the supporting structure will be driven into its final position in October 2025 using SPMTs (Self-Propelled Modular Transporters). A particular challenge for our assembly crew will be to install the bridge precisely during a shutdown period.

 

Special geometry of the bridge requires a high degree of precision from our welders

After 10 weeks of production, the foot and cycle path bridge over the B426 in Mühltal, Hesse, was lifted into place in the night of 16 to 17 February 2024. The bridge has created a publicly accessible footpath and cycle path between Rheinstraße and the Ruckelshausen business park, which also provides access to the Riese & Müller company car park.

The biggest challenge when lifting the centre section of the bridge was to simultaneously insert the 4.5 m wide and 23 m long steel structure into six differently orientated supports with the help of two cranes during the lowering process. The two stairway sections were placed to the north and south of the bridge during the night and will be welded in place over the next few days. A total of 114 tonnes of steel were used for the bridge, including the superstructure, stairs, supports, railings and steps.

Special praise is due to the welding specialists at Donges SteelTec. They met the special welding requirements of the geometrically demanding steel bridge with great precision.

 

Sophisticated assembly concept – Donges SteelTec scores with many years of experience and expertise in bridge construction

The consortium consisting of Adam Hörnig GmbH and Donges SteelTec GmbH was commissioned by the federal motorway authority Autobahn GmbH with the replacement construction of the Main bridge near Mainflingen. Our company’s expertise and many years of experience in the field of bridge assembly was a particularly important aspect in the successful acquisition of the contract.

The old Main bridge at Mainflingen on the BAB 45 motorway is being replaced by an elegant bridge with a tensioned chord structure.

At the location of the bridge, the River Main forms the state border between Mainhausen in Hesse and Kleinostheim in Bavaria. A slender steel composite construction and the low overall height of the bridging structure ensure that the replacement structure blends harmoniously into the varied river landscape.

The two superstructures have a total length of 450 metres. The 260 m long river bridge is designed as a three-span continuous girder in pure steel construction for the main supporting girders in the longitudinal direction of the bridge and in composite steel construction for the cross girders and carriageway slab structure. The supporting structure consists of a steel trough with box-shaped longitudinal girders and is spanned by chords, which are also box-shaped. The tension chord construction allows a slender centre span of 135.00 m above the river Main with two equal side spans of 62.50 m each. The slenderness in the centre of the span is approx. L/45. The tension chords are supported by approx. 15.00 m high pylons.

The displacement of the pylon locations compared to the existing structure results in a symmetrical situation along the Main axis.

The installation specialists from Donges SteelTec face a particular challenge. Due to the one-piece cross-section of the existing bridge, it is not possible to demolish half of it. The first superstructure (RiFa Gießen) of the A45 over the Main must therefore be built in a lateral position and later shifted crosswise over a length of 450 metres. The assembly of the steel structure is just as challenging. This will be constructed at the final position above the foreland on both sides of the Main on skidways and shifted longitudinally over the Main. The approx. 500 tonne centre section is then floated in over the Main, lifted and welded.

The entire construction project will last until 2031 and is an important milestone in the redevelopment of the German bridge landscape.

Donges SteelTec manufactures and assembles the steel structures for nine railway bridges

In the course of the flood disaster in July 2021, large parts of the Deutsche Bahn rail network in the Ahr valley were destroyed. Now, bridges and railway embankments along the route are to be rebuilt in a highly water-resistant manner. The main focus is on the bridges. The former round arch bridges are to be given a slimmer construction during the reconstruction in order to offer the (flood) water as little surface of attack as possible.

Donges SteelTec has been commissioned to manufacture, deliver and assemble the steel structures (4300 t) for nine steel trough bridges. The contract also includes workshop and assembly planning as well as all corrosion protection services, bearings, transition structure and railings.

We are pleased to be able to contribute to the reconstruction of the Ahr valley and are convinced that the decision to build the new bridges sustainably in steel construction is an additional measure to increase resilience against possible future flood events.

 

Donges pushes bridge Overfly over Nuremberg East interchange

The bridge structure 3-1 Overfly transfers an exit of the motorway A6 Rifa Amberg over the motorway junction Nuremberg East and thus reconnects the motorway A6 to the motorway A9. The new construction will improve the performance of the Nuremberg East junction.

The bridge construction is a combination of continuous girder and cable-stayed bridge and can therefore be classified as an extradosed bridge. Donges SteelTec is constructing the complete bridge in the so-called cycle basement in 6 sections. After assembly, each section is hydraulically shifted longitudinally over the abutment and the concrete piers. The next section is then connected to the displaced end of the previous section until the opposite abutment is reached.

The steel composite structure, 588 m long in total, impressively spans the 115 m span with a total of 5 pairs of pylons. Up to 55 stranded cables form the cables of the stay cables. A total of approx. 8,600 tons of steel will be used for the 588 m long bridge.

The displacement of the bridge, including the already assembled pylons and cables, is carried out in 6 cycles with the maximum displacement distances of 115 m. A 50 m long cantilever bridges the free spans during shifting and compensates for the deflections of the bridge due to its own weight when it runs onto the next pier. Shifting takes two days per cycle. It takes place on special shifting rockers and is carried out with the help of greased shifting plates that allow the steel construction to slide forward successively. In this way, the shifting load that the hydraulic presses have to apply can be reduced to a maximum of 10 % of the bridge weight.

On 22.06.2023 the 3rd shifting cycle was successfully completed, the next components of the 4th cycle are currently being assembled. The steel construction work will continue until 2024.

 

Donges SteelTec builds bar arch bridge for the Regionaltangente West (RTW) in Frankfurt am Main

An impressive bar arch bridge is currently being built at the Frankfurt Stadion S-Bahn station and thus right in front of the Waldstadion Frankfurt. The bridge structure carries the new RTW line over the existing Deutsche Bahn AG track system.

The superstructure of the bar arch bridge with a span of approx. 113 m is being built in steel construction and is divided into two arch levels consisting of stiffening girders, arches and hangers, as well as an orthotropic carriageway and walkways with cable ducts on both sides.

Design, fabrication and corrosion protection of the steel components were carried out at the Donges SteelTec GmbH plant in Darmstadt.

Parallel to the fabrication, the individual foundations were produced on the construction site and the auxiliary scaffolding was prepared for the erection. The steel structures were delivered by heavy-duty transporters to the pre-assembly site, where a mobile crane placed the components directly into the assembly position. Due to the very tight space conditions on the construction site, the pre-assembly began in the eastern area of the assembly area. Here, the first third of the superstructure with axis 10 was assembled in a horizontal position and then moved along the assembly area in a westerly direction using an SPMT (Self-Propelled Modular Transporter) so that the other steel sections could then be added.  Welding and corrosion protection work is currently underway on the site until autumn 2023.

For the actual insertion over the DB tracks in May 2024, the superstructure will be stacked in the storage axles to shunting height, transferred to SPMT and aligned in the shunting position. During a 24-hour break in rail traffic, the superstructure will be pushed over the track field with maximum cantilever and taken over on the opposite side by a lattice boom crawler crane.

We are very pleased to be able to carry out this exciting project close to home.